This page lists current & recent work being done on covered bridges or under design. If you are aware of any projects not included here, please notify us at nspcb@yahoo.com so they can be added.
For earlier entries, see the list of major covered bridge projects since 2010.
California | Maine | New Hampshire | Pennsylvania |
Illinois | Maryland | New York | Québec |
Indiana | Michigan | Ohio | Vermont |
Kentucky | New Brunswick | Oregon | West Virginia |
World Guide Number | Last Updated | ||
California |
|||
CA/05-04-01 |
Honey Run Bridge Fundraising to replace the Honey Run Bridge lost on November 8, 2018 during the devastating Camp Fire in Butte County in northern California continues. The first task, building the new abutments and piers has been completed. Future progress will start when money is available. Checks and inquiries regarding donations may be sent to: Honey Run Covered Bridge Association, P.O. Box 5201, Chico, CA 95927. |
Fundraising underway | November 23, 2022 |
Illinois |
|||
Indiana |
|||
IN/14-21-01 |
Longwood Bridge The project is primarily repairing or replacing components constructed when the bridge was relocated in 1984. The bottom chord added at that time was not as substantial as the one originally constructed by the Kennedy’s a hundred years earlier and is being replaced. End posts and arch ends will also be replaced. While the structure is raised for those repairs, the abutments will be replaced. They were also not suitable for the structure and are failing as a result. Finally, a donation of fire retardant has been approved. |
Repairs Nearly Complete | May 12, 2024 |
IN/14-23-02 |
Cades Mill Bridge The Fountain County Historical Committee has raised sufficient funds to begin work on this project. Work is planned to begin in June 2024. Additional donations are still needed. Donation checks towards the project should be made out to Western Indiana Community Foundation and sent to them at P.O. Box 75, Covington, IN 47932. Be sure to note that it is for the Cades Mill Bridge project. |
Repairs to begin soon, Fundraising Underway | May 12, 2024 |
Kentucky |
|||
KY/17-35-05 |
Grange City Bridge After spring flooding badly damaged an already crumbling abutment causing the bridge to drop a couple feet, Graton Associates were hired to perform emergency repairs. The bridge was stabilized on July 1, 2020 and underwent additional repairs in the fall of 2020. A full restoration of the bridge is underway. |
Repairs Underway. | May 12, 2024 |
Maine |
|||
Maryland |
|||
Michigan |
|||
MI/22-75-01 |
Langley Bridge The
$3.2 million project to repair the steel beams supporting the bridge and
its abutments has been completed and the bridge was re-opened to traffic
on January 12, 2024. |
Repairs Completed | January 12, 2024 |
New Brunswick |
|||
NB/55-02-15 & NB/55-15-12 |
Benton Bridge The bridge received a new roof, siding and some truss repairs.
Work was completed during the winter and early spring. |
Repairs Completed | April 29, 2024 |
New Hampshire |
|||
NH/29-02-08 |
Whittier Bridge The project to put the bridge back over the river was completed in November 2022. |
Repairs Complete | November 23, 2022 |
New York |
|||
North Carolina |
|||
Ohio |
|||
OH/35-04-19 |
Harpersfield Bridge In 2016, county engineers proposed to replace the bridge with a new one. Due to strong opposition, a major renovation was proposed. The intent is to maintain the single lane configuration; removal, rehabilitate and restore the steel truss span; rehabilitate the wooden truss in-place including the addition of steel under-floor support beams; add a pedestrian walkway to the upstream side; replace both abutments and replace the existing 4 steel and 2 concrete piers with new concrete piers. |
Repairs Nearly Complete | May 12, 2024 |
OH/35-14-11 & OH/35-36-06 |
Lynchburg Bridge The Righter Company has removed and replaced damaged members, salvaged existing members as much as possible, all while using authentic original construction methods. The bridge has been moved back over the river and received new decking. The new roof remains to be completed. They expect the project to be completed by mid-December. |
Repairs Underway | November 23, 2022 |
OH/35-56-18 |
Knowlton or Long Bridge Monroe County commissioners have decided to replace the covered bridge which partially collapsed in July 2019. A second span collapsed in June 2020. The article did not indicate if the entire bridge was to be replaced, or only the collapsed spans. The county plans to use timber from a county-owned lot for the repairs which may go out to bid in spring 2023. |
Repairs planned | November 23, 2022 |
Oregon |
|||
OR/37-22-03#2 |
Shimanek Bridge Lane County, OR The bridge was moved off of its abutments so it’s piers and approaches could be reconstructed. While the bridge was on dry land, its lower chords were replaced. Due to the difficulty of obtaining new Douglas fir timbers of sufficient size for the job, they were replaced by glulam beams. The upper chords and diagonal timbers also needed some repair due to decay. The entire truss was tuned to a desired camber and chemically fumigated to minimize future insect damage. Once back over the river, new siding was added and then the new roof. Due to slow supply chain issues and difficulties finding enough skilled laborers, the completion date was moved to late November. |
Repairs Completed | December 17, 2022 |
Pennsylvania |
|||
PA/38-09-05 |
South Perkasie Bridge Bucks County, PA Perkasie Borough, the Bucks County Covered Bridge Society and Perkasie Historical Society combined efforts to raise $100,000 to qualify for a matching Pennsylvania Historical and Museum Commission Keystone Historic Preservation Construction Grant for repairs to the bridge. The $100,000 grant was awarded on September 9, 2020. |
Repairs Planned | November 23, 2022 |
PA/38-39-01 |
Bogert's Bridge Allentown, PA Approximately $1.165 million has been raised so far towards the project to restore the bridge. An estimated $1.5 million is needed to fully restore the bridge. |
Fundraising Underway | November 23, 2022 |
PA/38-60-01#2 |
Millmont or Red Bridge Union County, PA On July 7, 2020, Union County Commissioners voted to contract with Larson Design Group to design repairs for this bridge estimated at $163,231. The bridge was rebuilt by Lycoming Supply Inc. of Williamsport, Pennsylvania in 2010. More than 50% of the bridge’s truss system was replaced at that time. On March 18, 2016, PennDOT and Union County engineers decided to close bridge deeming it unsafe for vehicle traffic. They had been watching the bridge for the previous year due to concerns for structural problems. |
Repairs Planned | July 20, 2020 |
Québec |
|||
QC/61-06-01 |
Pont Perrault
The municipality of Notre-Dame-des-Pins is contacting local businesses to
help fund the repairs to this bridge. It has been closed to all traffic and pedestrians since February 2018. Prior studies have evaluated the needs of the bridge and the results of these studies will be used to prepare plans and specifications. They are targeting to have the bridge open again
in 2023.
Chaudière - Appalaches Region, QC |
Work underway | December 17, 2022 |
QC/61-53-01 |
Félix-Gabriel-Marchand Bridge
The bridge was closed for safety reasons in May 2014 after a structural
evaluation. A repair project began in April 2018 and has progressed slowly
since then. Mansfield et Pontefract, QC |
Repairs Complete | December 17, 2022 |
Vermont |
|||
VT/45-03-07 |
Sanborn Bridge
Fundraising is underway for repairs to the bridge. Temporary repairs
were funded by the NSPCB in 2013. It is time for the complete
repairs estimated at $1.3 million.Lyndon, VT |
Fundraising underway | December 17, 2022 |
VT/45-03-07 |
Randall Bridge
Bridge closed to all traffic and use. Rehabilitation of the bridge for use
as a pedestrian and trail (snowmobile) crossing. Rehabilitation design by
DuBois & King, Inc. Work to include repair to roof framing, trusses, floor
framing, concrete abutments, and approach pathway.Lyndon, VT |
Conceptual design complete | December 17, 2022 |
West Virginia |
|||
WV/48-01-02 |
Carrollton Bridge The bridge received extensive damage from an arson fire on August 10, 2017. Repairs are underway by the West Virginia DOT. |
Repairs underway | December 17, 2022 |