National Society for the
This page lists current & recent work being done on covered bridges or under design. If you are aware of any projects not included here, please notify us at nspcb@yahoo.com so they can be added.
For earlier entries, see the
list of major covered bridge projects since 2010.![]()
| California | Maine | New Hampshire | Pennsylvania |
| Illinois | Maryland | New York | Québec |
| Indiana | Missouri | Ohio | Vermont |
| Kentucky | New Brunswick | Ontario | West Virginia |
| World Guide Number | Last Updated | ||
|
Illinois |
|||
| IL/13-06-01 |
Red Bridge After being severely damaged by a tractor-trailer on November 16, 2023, a crew from the Illinois Department of Transportation installed temporary shoring in December 2023 to stabilize the roof. The structure was evaluated and repairs are being designed. |
Repairs in Design Stage | February 8, 2026 |
| IL/13-79-01 |
Little Mary 's River Bridge A storm tore the roof off of this bridge near Chester on July 1, 2023. After being exposed to the elements for over a year, repairs are now underway. Samron Midwest Contracting from Murphysboro, Illinois, was awarded a contract for $311,702 for the repair work. In addition to replacing the roof, they added a fire suppression and security system. The project was completed in September 2025. |
Project Completed | October 8, 2025 |
|
Indiana |
|||
| IN/14-23-02 |
Cades Mill Bridge The Fountain County Historical Committee has raised sufficient funds for this project. Work was completed in the spring of 2025 with a ribbon-cutting celebration on June 8, 2025. |
Repairs Complete | June 12, 2025 |
| IN/14-29-14 |
Bell's Ford Bridge The Bell's Ford Bridge which originally stood in Jackson County, Indiana, has been rebuilt as a pedestrian bridge in Fishers, Hamilton County, Indiana. This is the only Post truss covered bridge. The project was completed in early 2025. |
Project Complete | June 12, 2025 |
| IN/14-49-07 |
Traders Point Bridge On August 18, 2025, Indiana Landmarks announced that bridge was included on its annual compilation of the state’s "10 Most Endangered" landmarks. Originally built over Fishback Creek, it was moved about 0.6 miles to its present location in 1960. In 2022, Indiana Landmarks hired Kurdziel Barker Engineering to conduct a cost study to rehabilitate and move the bridge to Eagle Creek Park. The firm estimated it would cost $1.3 million to dismantle the bridge, move it and put it back together in Eagle Creek Park. It would cost another almost $500,000 for maintenance like a new roof and sidings. Design costs would add another $170,000. The Lilly Foundation has already pledged $1 million towards the nearly $2 million project. |
Fundraising Underway | February 8, 2026 |
| IN/14-61-26 |
Melcher Bridge The abutments of this bridge had deteriorated to the point where they needed to be replaced. The repair project began in 2024 and is still underway. |
Project Underway | May 12, 2025 |
| IN/14-70-01 |
Smith or Ewbank Bridge The project to repair this bridge began in the summer of 2024 when it was moved off of its abutments. In March 2025, with repairs nearly complete, it was placed back on its abutments. |
Project Nearly Complete | June 20, 2025 |
|
Kentucky |
|||
| KY/17-35-04 |
Ringos Mill Bridge Sections of the upper and lower chords (particularly near the ends of the lowr chords) needed to be replaced. Some some floor joists were replaced and deteriorated sections of some vertical truss members spliced with new wood. The project is now complete and a celebration was held on October 3, 2025. |
Repairs Complete. | October 8, 2025 |
| KY/17-35-05 |
Grange City Bridge After spring flooding badly damaged an already crumbling abutment causing the bridge to drop a couple feet, Graton Associates were hired to perform emergency repairs. The bridge was stabilized on July 1, 2020 and underwent additional repairs in the fall of 2020. A full restoration of the bridge is now complete a celebration was held on October 3, 2025. |
Repairs Complete. | October 8, 2025 |
|
Maine |
|||
|
Maryland |
|||
|
Missouri |
|||
| MO/25-58-01 |
Locust Creek Bridge On February 26, 2025, the bridge was moved to a new
location in Pershing State Park where it will become the trailhead for the
park's riparian trail. |
Relocation Underway | February 26, 2025 |
|
New Brunswick |
|||
| NB/55-14-13 |
Wheaton or Tantramar River #2 Bridge The bridge was closed on July 11, 2024 due to safety concerns. The New
Brunswick Department of Transportation and Infrastructure is planning to
install a modular bridge next to it for traffic and restore the covered
bridge for pedestrian use. |
Bypass Planned | May 12, 2025 |
|
New Hampshire |
|||
|
New York |
|||
|
North Carolina |
|||
|
Ohio |
|||
| OH/35-56-18 |
Knowlton or Long Bridge Monroe County commissioners have decided to replace the covered bridge which partially collapsed in July 2019. A second span collapsed in June 2020. The remaining span was repaired and two new spans constructed. The county used timber from a county-owned lot for the repairs. The project was completed in the fall of 2024. |
Project Completed | October 20, 2024 |
|
Ontario |
|||
| ON/59-50-01 |
West Montrose Bridge Waterloo County, ON Repairs to this span have begun. The work will include removal of the steel Bailey truss which had provided part of the structures support along with other repairs. The project was advertised in spring 2025 and is expected to be completed near the end of 2026. |
Repairs Underway | October 8, 2025 |
|
Pennsylvania |
|||
| PA/38-09-05 |
South Perkasie Bridge Bucks County, PA Perkasie Borough, the Bucks County Covered Bridge Society and Perkasie Historical Society combined efforts to raise money and obtain grants for repairs to the bridge. The project design is complete and it is expected to go to bid soon with construction later in 2025. |
Repairs Anticipated | May 15, 2025 |
| PA/38-15-01#2 |
Rudolph and Arthur Bridge Chester County, PA The historic covered bridge was washed away by floodwaters on September 1, 2021. A project is underway to construct a replica. |
Construction Nearly Complete | October 8, 2025 |
| PA/38-32-05 |
Kintersburg Bridge Indiana County Indiana County Parks & Trails has secured $807,314 to restore and repair the bridge — one of only four Howe truss bridges remaining in Pennsylvania. Lancaster County Timber Frames of York, Pennsylvania is doing the work. |
Project Underway | February 8, 2026 |
| PA/38-39-01 |
Bogert's Bridge Allentown, Lehigh County, PA Design of the repairs to this bridge are complete and the project is underway. Construction is exected to be completed by the end of August 2026. |
Project Underway | October 8, 2025 |
|
Québec |
|||
| QC/61-01-05 |
Pont Alphonse-Normandin
The
bridge was moved off of its abutments in the summer of 2023 for repairs.
Repairs were completed and the structure moved back into place in the
summer of 2024. After a delay of over a year, the project got underway
again on July 14, 2025.Abitibi-Témiscamingue Region, QC |
Work underway | July 15, 2025 |
| QC/61-72-01 |
Pont Prud'homme Bridge
The bridge was closed to traffic for safety reasons in 2019. Repair work
has been delayed since then and is currently anticipated for sometime in
2027. Laurentides Region, QC |
Repairs Anticipated | February 8, 2026 |
|
Vermont |
|||
| VT/45-01-01 |
Salisbury Station Bridge
After being consumed by fire on September 10, 2016, plans have been in the works to construct a replica
of the historic covered bridge. Due to federal budget cuts, the project
has been delayed until 2031.Addison County, VT |
Project in Design | May 15, 2025 |
| VT/45-03-05 |
Sanborn Bridge
In the summer of 2024 the bridge was removed from ita abutments and
dismantled. The project to reconstruct it on new abutments is in the
design stage with advertising anticipated in late 2025 or early 2026.Lyndon, VT |
Project in Design | August 15, 2025 |
| VT/45-03-07 |
Randall Bridge
Bridge closed to all traffic and use. Rehabilitation of the bridge for use
as a pedestrian and trail (snowmobile) crossing. Rehabilitation design by
DuBois & King, Inc. Work to include repair to roof framing, trusses, floor
framing, concrete abutments, and approach pathway.Lyndon, VT |
Conceptual design complete | December 17, 2022 |
| VT/45-04-05 |
Westford or Brown's River Bridge
On May 22, 2025, the Selectboard approved a contract with Vermont Heavy Timber of Huntington
for repairs to the bridge which will include repairing structural damage
to the Burr arches, bolster beams, bearing blocks and joists, as well as
flashing and sheathing utilizing protective measures to prevent future
damage.
Westford, VT |
Repairs underway | February 8, 2026 |
|
West Virginia |
|||